Thursday, November 25, 2010
Who says you need a kitchen to host Thanksgiving?
The Turkey is on the BBQ, the table is set. Tons of candles for when it gets dark with no lights! Bring it on!
Wednesday, November 24, 2010
week 4 Cab Installation DEFINITELY NO TURKEY HERE
Tuesday, November 16, 2010
Finishing the Sheetrock Bring On the Mud & Tape!!
Saturday, November 13, 2010
11/13 End of week 2
Wednesday, November 10, 2010
Progress,Island Hood installed
Tuesday, November 9, 2010
Saturday, November 6, 2010
MY KITCHEN End of Week One
Plumbing rough in nearly complete on appliance well. Copper pipes are for Main Refer. Ceiling shows recessed housing for lights which will all be energy compliant LED fixtures.
Problems of the week: windows delayed, wine refer never made it onto the final order, sump pump now installed under house, tree roots have invaded drainage pipes.
Next week: finish electrical installations for 1st inspection before closing ceiling/walls
Thursday, November 4, 2010
H2 under consideration for 2011 NKBA Awards
Day 4
Monday, November 1, 2010
Subscribe to: